HOME PAGE SUBSCRIPTIONS, Print Editions, Newsletter PRODUCTS READ THE PETROLEUM NEWS ARCHIVE! ADVERTISING INFORMATION EVENTS

Providing coverage of Alaska and northern Canada's oil and gas industry
August 2014

Vol. 19, No. 34 Week of August 24, 2014

Tall stack of authorizations await

The Alaska LNG project faces formidable permitting; below is a primer on the federal agencies whose approvals would be required

Bill White

Researcher/writer for the Office of the Federal Coordinator

The multibillion-dollar Alaska LNG project aims not only to tap the North Slope’s bounty of natural gas, pipe it to tidewater and superchill the vapors into a condensed liquid for export to Asia markets.

The project also aims to tap a bounty of public resources: land, wetlands, gravel, lakes and ponds, streams and rivers, possibly even the ocean itself. And to tap them, the project sponsors would need a stack of permits and authorizations from a variety of government agencies.

During construction and operations, the system’s machinery, like any industrial activity, would create emissions that would alter air quality. Public soils and vegetation would be disturbed, at least temporarily. The project would cross paths with threatened and endangered species, and other fauna under public protection.

The project’s sponsors cannot use the public’s land, water and other resources without permission. It can’t change the air quality or water quality without a public process finding that such changes would be acceptable, findings that likely would come with strings attached.

The project’s pipeline can cross the Yukon, Tanana or Susitna rivers only after demonstrating this won’t impair the navigability of those waterways.

The gas liquefaction plant cannot start production without a determination that it can be run safely.

The gas itself cannot be shipped away from the United States without consideration of whether the export would harm U.S. consumers.

Even the president, under a 1976 law, would have a special say on the export of North Slope gas, a unique feature of the Alaska project that doesn’t exist for Lower 48 liquefied natural gas projects.

To say that the Alaska LNG project would need federal paperwork is to understate the matter, like saying the Pentagon is roomy or monsoon season is damp.

The estimated $45 billion to $65 billion Alaska LNG project would involve integrating several major undertakings: Gas production from two North Slope fields, a gas treatment plant at Prudhoe Bay to remove impurities, an 800-mile buried pipeline, and an LNG plant and export terminal at Nikiski.

The sponsors know the task ahead to receive the authorizations needed for their project. And they have begun gathering the environmental data regulatory agencies will want to see.

Permits before construction

More than a half dozen federal agencies would issue major authorizations for the Alaska LNG project before construction could begin. These include:

•Federal Energy Regulatory Commission - to authorize siting, construction and operation of the LNG plant and likely the 800-mile pipeline from the North Slope to the plant. FERC also would take the lead on a consolidated environmental impact statement researched and written on behalf of itself and other federal agencies.

•Bureau of Land Management - to grant use of federal land for the pipeline, construction camps, staging yards, gravel mining and water extraction.

•U.S. Army Corps of Engineers - to issue dredge and fill permits pertaining to wetlands, rivers and offshore areas.

•Environmental Protection Agency - to permit disposal of sediment dredged from the Beaufort Sea if needed to create a deeper shipping channel for sealifts to deliver construction materials and equipment to the North Slope.

•Fish and Wildlife Service and National Marine Fisheries Services - to authorize isolated incidents of harm or death of marine mammals, endangered species or other protected animals.

•Pipeline and Hazardous Materials Safety Administration - to ensure the gas pipeline would be built and operated to federal safety standards.

•Coast Guard - to ensure any bridging of rivers would not impair the waterway’s navigability, document the suitability of Cook Inlet to handle LNG tanker traffic, consult with the project sponsor on the LNG terminal’s emergency response plan and approve the terminal’s security plan.

•Department of Energy - to authorize gas exports.

Other federal agencies could lay their fingerprints on the project, too. For example, the Federal Communications Commission for radio communications, the Federal Aviation Administration for building or altering airstrips, Homeland Security for the vulnerability of facilities to attacks, or the Bureau of Indian Affairs for rights of way on any Alaska Native allotments the pipeline could cross.

State of Alaska agencies would have the lead on air, water and wastewater permits, under authority delegated from the EPA, as well as use of state land.

Federal agencies and the project sponsors also must consult with the Alaska Historic Preservation Office on any historic or archeological sites the project would encounter during construction. Part of the project’s field-season work in past years has been to identify such sites so the pipeline route and other land use can skirt them. Encountering them during construction could involve delays while preservation officers decipher a site’s significance.

Déjà vu, and then some

Federal agencies have seen Alaska North Slope gas projects before. Over the years, quite a few of them have burst into headlines like supernovas, before eventually flaming out.

For the most recent proposal to pipe North Slope gas through Canada to North American consumers, about two dozen federal agencies had lined up for permitting work before the pipeline sponsors shelved the project in 2012.

The Alaska LNG export project would engage many of these same agencies. A substantial portion of it is essentially identical to the project to serve North America: A huge plant at Prudhoe Bay to cleanse produced gas of impurities, and half of the pipeline route - as far as the Fairbanks area.

Alaska LNG proposes a $45 billion to $65 billion venture that would be one of the world’s largest LNG projects.

The 800-mile pipeline would carry up to 3 billion to 3.5 billion cubic feet of natural gas per day. After Alaskans, the pipeline compressor stations and LNG plant at Nikiski consume some gas, the plant would have the capacity to make 17 million to 18 million metric tons a year of LNG, about 2.2 billion to 2.4 billion cubic feet of gas a day.

The sponsors are the main North Slope producers - ExxonMobil, ConocoPhillips and BP - as well as pipeline company TransCanada and the state of Alaska. (TransCanada and ExxonMobil sponsored the 2012-shelved pipeline to Canada. ConocoPhillips and BP also sponsored a project to move North Slope gas through Canada that couldn’t pass the economics test and was dropped in 2011.) They are in the pre-front-end engineering and design phase, or pre-FEED, which is expected to be completed in late 2015 or 2016. If the project looks financially viable, next would be FEED of perhaps two years or so, when many of the pre-construction federal authorizations would be obtained. Construction could start toward the end of this decade if the project keeps progressing.

Below is a brief guide to the federal agencies that would be involved with the major Alaska LNG authorizations.

Federal Energy Regulatory Commission

This commission would do some of the heaviest lifting in overseeing the Alaska LNG project.

It would authorize the siting, construction and operation of the LNG plant and related facilities and take the lead in crafting the environmental impact statement that multiple agencies require for their authorizations.

It’s likely that FERC would consider the 800-mile pipeline and the gas treatment plant at Prudhoe Bay as “related facilities” to the LNG plant in preparing a single environmental impact statement. The argument would be strong that these would exist primarily to feed gas to the LNG plant, making them integral to the plant’s function. FERC won’t consider and decide whether they’re related facilities until the Alaska LNG sponsors ask the commission for permission to pursue the LNG project. FERC would have to interpret the legal definition of “LNG terminal,” which was broadly written by Congress in a 2005 law.

If FERC declines the pipeline and treatment plant oversight, another federal agency or agencies with substantial jurisdiction, such as the Corps of Engineers or Bureau of Land Management, likely would lead separate environmental impact statement(s) for those pieces.

For the LNG plant, FERC would review design and engineering of the three big LNG production lines, called trains, that chill incoming gas to minus 260 so that the vapors liquefy and condense; cryogenic piping and insulation; refrigerant tanks; LNG storage tanks; pumps; meters; boil-off-gas compressors; a pier for two tankers; utilities. That’s just a sampling.

FERC would evaluate how construction could affect geology, soils, water and air quality, noise levels, wetlands, vegetation, wildlife, threatened or endangered species, essential fish habitat, land use and recreation, among other possibilities.

For the pipeline, gas treatment plant and other related facilities, the breadth of oversight would be just as vast. The environmental impact statement could cover temporary and permanent roads, bridges and water-body crossings, material sites, pipe-storage yards, contractor yards, worker camps, compressor and metering stations, control rooms, regulating stations, helipads, dredge channels, ocean-disposal sites, ice/snow pads, pipeline trenching - to name some.

FERC requires project sponsors to pre-file with the commission ahead of formally filing for authority to build an LNG plant. During the months-long pre-file period, the sponsor compiles specific baseline information on the project and the surrounding environment. The energy commission and other regulatory agencies can then verify and use that baseline information for the environmental-impact analysis. The sponsors compile this information in dense public documents called “resource reports.”

For the unsuccessful North Slope-to-Canada gas pipeline project, the TransCanada-ExxonMobil team filed 11 draft resource reports in January 2012. They tallied about 4,500 pages. Much of this information likely can be used for the Alaska LNG project. More info will need to be gathered for other parts of the pipeline route and the LNG plant site.

The environmental analysis is a key stepping stone to getting FERC approval. When FERC approved construction of Cheniere Energy’s Sabine Pass, Louisiana, LNG export plant in 2012, its 57-page order finding the project is “not inconsistent with the public interest” largely discussed the environment-impact analysis. That plant now is getting built, and Cheniere says it will make its first LNG in late 2015.

Such analyses are mandated in the National Environmental Policy Act, which became law in 1970. It requires federal agencies understand and disclose the environmental consequences of their decisions. The law gave birth to the phrase “environmental impact statement” ... and the big industry that since has built up around that mandate.

Many federal agencies besides FERC would have their own NEPA roles related to Alaska LNG. They likely would sign on as cooperating agencies for the impact statement.

FERC would try to make sure the EIS is comprehensive enough to serve as BLM’s NEPA document, as well as the document needed by the Corps of Engineers, Fish and Wildlife Service, National Marine Fisheries Service, Coast Guard and others for the permits and authorizations they issue.

FERC and other agencies have been collaborating on NEPA reviews of proposed Lower 48 LNG export plants for several years. But the scale of Alaska LNG would be far grander than, for example, the roughly $10 billion Cameron LNG project in Louisiana or the $4 billion Dominion Cove Point LNG project in Maryland. Each of those had four cooperating federal agencies for their FERC-led environmental reviews completed in spring 2014.

Alaska LNG would have far more complexity. Greater footprint. Bigger potential environmental impact. FERC likely would be juggling the permitting interests of many more federal agencies. For the recently shelved gas-pipeline project from Prudhoe Bay to Canada, FERC was working with nine cooperating federal agencies on the EIS.

Many of FERC’s non-environmental requirements for interstate gas pipelines might not apply to an Alaska LNG export project if the pipeline and treatment plant are not deemed interstate facilities under federal law. These include FERC’s rules and policies on customer access (open seasons), rate regulation, tariff provisions and eminent domain.

Bureau of Land Management

The gas pipeline would cross hundreds of miles of federal land. BLM would grant the permit allowing use of this public land.

The Alaska LNG project sponsors would apply to use federal land for the pipeline corridor as well as for pipeline compressor stations, work camps, contractor and material yards, helipads, roads and the like related to construction.

In advance of construction, the sponsors would apply to use federal land temporarily for field work to study the route, ice and snow pads, and temporary roads, camps, contractor yards and pipe-storage areas.

BLM would work with other federal agencies if the pipeline route crosses land they oversee. The route likely would skirt two wildlife refuges and two national parks without entering them and completely bypass the big military bases by Fairbanks. It’s unclear how close the route would come to the Clear Air Force Station southwest of Fairbanks, but if the route penetrates that land, the Air Force would need to sign off on BLM’s right-of-way grant.

Separately, BLM permits the purchase and extraction of construction gravel from federal land under the Materials Act.

BLM would need to consider environmental impacts before acting on any of these permits. l

Editor’s note: This is a reprint from the Office of the Federal Coordinator, Alaska Natural Gas Transportation Projects, online at www.arcticgas.gov/tall-stack-authorizations-await-alaska-lng-project

Part 2 will run in the Aug. 31 issue.






Petroleum News - Phone: 1-907 522-9469 - Fax: 1-907 522-9583
[email protected] --- https://www.petroleumnews.com ---
S U B S C R I B E

Copyright Petroleum Newspapers of Alaska, LLC (Petroleum News)(PNA)©1999-2019 All rights reserved. The content of this article and web site may not be copied, replaced, distributed, published, displayed or transferred in any form or by any means except with the prior written permission of Petroleum Newspapers of Alaska, LLC (Petroleum News)(PNA). Copyright infringement is a violation of federal law subject to criminal and civil penalties.