Nanushuk, Liberty comment periods extended
The U.S. Army Corps of Engineers has extended the public comment periods for both the Liberty and Nanushuk projects.
The public comment period on the draft environmental impact statement for Armstrong Energy LLC’s Nanushuk project, released Sept. 1, was originally Oct. 15; it has now been extended to Nov. 14.
Public meetings on the Nanushuk draft EIS are scheduled for Sept. 25 in Nuiqsut, Sept. 27 in Utqiagvik, Oct. 3 in Fairbanks and Oct. 4 in Anchorage. For details see the project EIS website at www.NanushukEIS.com.
For Hilcorp Alaska LLC’s Liberty project, in August the Bureau of Ocean Energy Management initiated a 90-day public comment period ending Nov. 18. The Corps has now extended its public comment period to end at that time.
BOEM has public hearings scheduled on the Liberty draft EIS for Oct. 2 in Nuiqsut; Oct. 3 in Fairbanks; Oct. 4 in Kaktovik; Oct. 5 in Utqiagvik; and Oct. 10 in Anchorage. See details at: https://www.boem.gov/Hilcorp-Liberty/.
- Petroleum News
|