Logistics key to Point Thomson project Last year’s ice road only available to move materials for four weeks; barges used in summer; rolligons moved significant amounts Kristen Nelson Petroleum News
ExxonMobil has been fighting a running battle with the State of Alaska over development of its North Slope Point Thomson field — but it has also been waging a logistics battle to get equipment and supplies to the site which is 60 miles east of Prudhoe Bay on the coast of the Beaufort Sea just west of the Arctic National Wildlife Refuge.
Definitely not on the road system.
That logistics battle was the focus of an overview of the last 18 month’s work by Lee Bruce, ExxonMobil’s senior project manager for Point Thomson at the Resource Development Council annual conference Nov. 18.
The terms of an agreement with the State of Alaska — after the state terminated the Point Thomson unit for lack of development and took back the leases — allowed drilling on two of the leases provided that the wells were completed by the end of 2010 and production begins by the end of 2014.
Real drilling — targeted to the reservoir — began at Point Thomson in late November, as field operator ExxonMobil continues work it began there in July 2008. Initial surface drilling for two wells, to depths of some 5,000 feet, was completed in May and August. Drilling into potential hydrocarbon-bearing reservoirs at coastal fields can only be done in winter months.
The project’s central pad is “an old drilling site with a lot of residual equipment left over that we had to remove,” Bruce said. That work began in July 2008 and by September 2008 the pad was cleared and work had begun to prepare the pad for future work.
Transportation to Point Thomson is based on the season: Exxon Mobil had a significant barging operation that first summer followed by air and rolligon supply, and finally by trucking down a 60-mile-long sea ice road. Construction on the ice road began in February and it opened the first week in April, he said, and shut down May 1, allowing just four weeks to get materials trucked in for the drilling program.
Bear bypass Bruce said the ice road required 40 million gallons of seawater and 11 million gallons of fresh water to cap the sea ice. A nine-mile bypass had to be built when a denning polar bear was discovered. It cost an additional $10 million to build the bypass to maintain a one-mile radius distance from the bear.
Work at the central pad was going on concurrently with the ice road, with more than 12,000 insulated pads put down to protect the tundra and more than 1,800 rig mats to provide a solid foundation for work.
Modifications to the Nabors 27-E rig were completed in April and the rig was ready for mobilization. Bruce said modification costs, between ExxonMobil and Nabors, were more than $35 million.
The rig was moved from Deadhorse to the central pad via the sea-ice road — a total of nine modules weighing more than 4.7 million pounds.
The first well was spud May 8.
“We drilled and cased and cemented the surface hole in 14 days with 1 percent nonproductive time,” Bruce said. He called that level of productivity “a testament to the guys and gals that worked on the rig to get it ready to roll,” and said it was “a significant achievement for drilling this well.”
Summer barging There was a barging operation again this summer — 67 days, from July 17 to Aug. 25 and from Sept. 23 to Oct. 17.
“We had to stop and allow the Inupiat to do their whaling. And we were fortunate that they were able to get their whales in time and allow us to start barging again,” Bruce said.
More than 120 roundtrip barge runs were completed, each about 24 hours with eight hours of loading and unloading on each end. Six barges were used.
At the pad eight 200,000-gallon diesel storage tanks were installed, providing 1.6 million gallons of diesel, which was delivered in 189 tanker trucks.
It’s the equivalent of filling the tanks of 75,000 trucks, Bruce said.
Getting diesel to the site by barge was a logistics necessity, he said, because “there’s no way to get diesel out there now except by helicopters at 500 gallons a load.”
More than 400,000 gallons of potable water were also delivered by barge, along with 750,000 gallons of drilling fluids.
A thousand joints of tubular were moved, along with 22 loads of barite cement.
“We also pre-positioned all of our ice-road building equipment and our heavy well-capping equipment so we can meet the requirements of being able to cap a well in 15 days.”
Some 30,000 tons of equipment, materials and consumables were moved in the 67 days of barging.
“No one thought we could get it done, and again, we got it done just in time. I think the last barge run shut down because of the weather conditions deteriorating significantly out there in the middle of October,” Bruce said.
The second well was spud July 29. As with the first well in May, there was less than 1 percent nonproductive time.
Ready to go With the pad stocked for this winter’s work it’s “very tight quarters” on the 13-acre pad, Bruce said.
There are 137 people living at Point Thomson.
He said drilling was expected to resume Nov. 23.
Bruce said ExxonMobil has in hand all of the permits required for drilling and has begun facilities permitting.
“We’re very fortunate the Corps of Engineers project manager is right lockstep with us with an aggressive target to achieve a record of decision in August of 2011.”
That would be two years from the start of project permitting and “would be world-class performance,” he said.
ExxonMobil’s overall philosophy is one of engaging agencies early and of open transparent communication on the project, Bruce said. “That has served us well and I expect it’s going to continue to serve us well in the future.”
The Alaska Department of Natural Resources is a cooperating agency with the Corps of Engineers on permitting.
Both wells will be completed by year-end 2010, Bruce said. From 2010 to 2013 “we’ll complete our front-end engineering design work.”
“In 2011 we expect to start field construction. And we’re on target to have first production by year-end 2014,” he said.
ExxonMobil has spent $300 million in the last year on Point Thomson, Bruce said, 80 percent of those dollars in Alaska.
More than 1,700 people — including a team of more than 100 Exxon employees — have been directly involved with Point Thomson work so far.
In the winter of 2011-12, during facilities construction, about 600 workers are expected to be involved full-time.
After production begins 130-plus people are expected to be employed providing on-going daily operations and maintenance.
|