HOME PAGE SUBSCRIPTIONS, Print Editions, News Bulletin PRODUCTS READ MINING NEWS ARCHIVE ADVERTISING EVENT READ THE PETROLEUM NEWS, EXTENSIVE ARCHIVES! SUBSCRIBE TO PETROLEUM NEWS -BAKKEN-

Providing coverage of Alaska and Northwest Canada's mineral industry
July 2007

Vol. 12, No. 30 Week of July 29, 2007

MINING NEWS: Too soon to decide on Donlin, judge rules

NovaGold must wait until November deadline in joint venture agreement to see if Barrick fulfills its requirements at Alaska project

Sarah Hurst

For Mining News

A U.S. District Court judge in Anchorage has dismissed NovaGold’s lawsuit against Barrick Gold over the Donlin Creek project where the two companies are joint venture partners. Vancouver-based NovaGold had asserted that Toronto-based Barrick, the world’s largest gold producer, breached the terms of the companies’ Mining Venture Agreement. Judge Timothy Burgess ruled that Barrick has until Nov. 12, 2007 — the date stipulated in the MVA — to fulfill its obligations on the project, and the company’s success or failure cannot be assessed before that date.

“We are satisfied that the Alaskan court found in Barrick’s favor and has entirely dismissed NovaGold’s series of allegations,” Patrick Garver, Barrick’s executive vice president and general counsel, said in a release July 19. “We vigorously disputed NovaGold’s allegations that implied improper conduct by Barrick and we are glad that the federal court has dismissed this ill-conceived action.”

NovaGold’s management thinks Barrick won’t meet the Nov. 12 deadline to produce a feasibility study for Donlin and to make a decision to begin construction, which would enable Barrick to earn an additional 40 percent interest in the project on top of the 30 percent it has currently. “NovaGold believes Barrick cannot deliver a meaningful construction decision, plan or budget without completing the environmental assessment process. NovaGold believes Barrick cannot meet the back-in requirements as outlined in the Agreement,” NovaGold said in a July 19 statement.

Judge: November the milestone

“Any number of intervening events could occur between now and November 2007 to change the nature of this dispute,” Judge Burgess wrote in his ruling. “Therefore, interpreting the contract would not settle all aspects of the controversy, nor would it serve a useful purpose in clarifying the legal relations at issue. ... The parties have contracted to allow (Barrick) to perform, fail to perform, or elect not to perform under the contract until November 2007. No other milestones for performance were set in the agreement.”

Barrick has already fought out a failed takeover bid for NovaGold, and the companies also have a dispute over the Galore Creek project in northwestern British Columbia. Defeating a rival bid by NovaGold, Barrick bought most of the shares of Pioneer Metals, a junior that owns the Grace claims adjacent to Galore Creek. NovaGold hopes to locate its tailings facility on the Grace claims, but Pioneer argued that more exploration drilling should be done in the area. Barrick’s control of the Grace claims could hinder NovaGold’s plans for development of Galore Creek, where permits are in place and road construction has just begun.





Rock Creek sees fatalities; costs rise

Two iron workers died during construction of NovaGold’s Rock Creek mine near Nome July 19. Craig Bagley, 27, from Anchorage and Tyler Kahle, 19, from Wisconsin, both worked for Anchorage-based contractor Alaska Mechanical. They were attaching siding to the mill building and fell about 50 feet when the lift basket they were working in tipped over, according to troopers. An investigation of the incident is under way.

NovaGold will spend an additional $40 million to complete construction and commissioning of Rock Creek, the company said in its second quarter financial results July 16. A new internal project and construction management team identified the increased costs in a recent review, which will take the mine’s total capital cost estimate to $120 million.

“The increase is the result of a number of factors, including delays in permitting that pushed major civil construction into mid-winter, rising costs, unexpected repairs to and replacement of supplied equipment, and requirements for additional labor and man hours to meet the previously announced schedule,” NovaGold said. The project is on target to achieve production by the end of this year, the company added.

In the second quarter of 2007 NovaGold reported a net loss of $3.2 million, compared with a net loss of $8.6 million in the same period last year. NovaGold also announced the appointment of Susan Mathieu as its new vice president for environment and sustainability. Mathieu was previously with Centerra Gold working on projects in Kyrgyzstan and Mongolia.

—Sarah Hurst


Mining News North - Phone: 1-907 522-9469 - Fax: 1-907 522-9583
[email protected] --- http://www.miningnewsnorth.com ---
S U B S C R I B E

Copyright Petroleum Newspapers of Alaska, LLC (North of 60 Mining News)(Petroleum News Bakken)(Petroleum News)(PNA)©2013 All rights reserved. The content of this article and web site may not be copied, replaced, distributed, published, displayed or transferred in any form or by any means except with the prior written permission of Petroleum Newspapers of Alaska, LLC (Petroleum News)(PNA). Copyright infringement is a violation of federal law subject to criminal and civil penalties.