BP Exploration (Alaska) gets what it needed done this winterIn spite of late start due to weather, Greg Mattson tells Alliance, Northstar work ended up where it needed to be this winter, with pipelines, island in place Kristen Nelson PNA News Editor
By the end of April, the pipelines to Northstar were in place, hydrotested, pigged and filled with nitrogen, and sheet pile was being installed around Northstar island.
In spite of a two to three week delay in starting due to weather, BP Exploration (Alaska) Inc.’s Greg Mattson told the Alaska Supp....
[additional news subjects in this story]
Materials stockpiled on island EOR from the beginning Project cost up from original estimates
You must be logged in to view this story. Please either log in or subscribe.
Click here to subscribe to Petroleum News for as low as $69 per year.
Subscribers log in here to read the entire newspaper (1998 to 06/24/2013)
Print this story | Email it to an associate.
Petroleum News - Phone: 1-907 522-9469 - Fax: 1-907 522-9583 [email protected] --- http://www.petroleumnews.com --- S U B S C R I B E
Copyright Petroleum Newspapers of Alaska, LLC (Petroleum News)(PNA)©2013 All rights reserved. The content of this article and web site may not be copied, replaced, distributed, published, displayed or transferred in any form or by any means except with the prior written permission of Petroleum Newspapers of Alaska, LLC (Petroleum News)(PNA). Copyright infringement is a violation of federal law subject to criminal and civil penalties.
|