RCA lets Chugach recover contract costsUtility can include $197M in future rates, AG and dissenting commissioner say RCA didn’t have enough time to deliberate Eric Lidji For Petroleum News
Chugach Electric Association will be allowed to pass on nearly $200 million in contracts for a new power plant to its ratepayers, according to a ruling by Alaska regulators.
The Regulatory Commission of Alaska on Oct. 5 decided that Chugach could recover the $197 million cost of three equipment and....
[additional news subjects in this story]
Lisankie writes dissent MetLife wouldn’t finance
You must be logged in to view this story. Please either log in or subscribe.
Click here to subscribe to Petroleum News for as low as $69 per year.
Subscribers log in here to read the entire newspaper (1998 to 06/24/2013)
Print this story | Email it to an associate.
Petroleum News - Phone: 1-907 522-9469 - Fax: 1-907 522-9583 [email protected] --- http://www.petroleumnews.com --- S U B S C R I B E
Copyright Petroleum Newspapers of Alaska, LLC (Petroleum News)(PNA)©2013 All rights reserved. The content of this article and web site may not be copied, replaced, distributed, published, displayed or transferred in any form or by any means except with the prior written permission of Petroleum Newspapers of Alaska, LLC (Petroleum News)(PNA). Copyright infringement is a violation of federal law subject to criminal and civil penalties.
|