Planning ahead

ConocoPhillips’ strategy for Chukchi Sea drilling in 2014 takes shape

Alan Bailey

Petroleum News

ConocoPhillips is moving ahead with plans for exploration drilling in Alaska’s Chukchi Sea in the summer of 2014, Mike Faust, the company’s Chukchi Sea exploration project manager, told the National Marine Fisheries Service’s annual Arctic Open Water Meeting on March 7.

“Our goal is to drill one well,” Faust said, adding that, although it might be possible to drill two wells during the summer open water season, the drilling of one well would meet the company’s expectations.

ConocoPhillips’ drilling target is its Devil’s Paw prospect, a 200,000-acre structure about 120 miles west of the coastal village of Wainwright. Devil’s Paw was previously penetrated by the Klondike well, drilled by Shell in 1989. And although that well did not encounter commercial quantities of oil and gas, ConocoPhillips clearly views the prospect as holding promise for a major oil find — the Devil’s Paw feature is similar in size to the huge Kuparuk River field in the central North Slope, Faust said.

Jack-up rig

Faust said that ConocoPhillips is contracting a brand-new, state-of-the-art jack-up rig from Noble Corp. for the drilling.

“They’re building six of them and we’re getting one of the rigs fresh out of the yard,” Faust said. “We’re not going to bring up a 30-year-old piece of equipment. We’re bringing up state-of-the art new stuff that is meant to work in the Arctic.”

The rig will have the latest features for safety and environmental protection, he said.

A jack-up rig is a floating structure that is towed into position at a drilling site, where tall legs are lowered into the water to the seafloor to lift the rig’s drilling platform above the sea surface, thus creating a rigid, fixed structure from which to drill. And because the bulk of the structure is above the water, the drilling operation transmits less sound into the sea than a similar operation in a floating drillship, Faust explained.

The new rig will be extremely strong; it is designed for use in the North Sea where wave heights can be significantly higher than anything seen in the Chukchi Sea, with the drilling platform typically 40 to 60 feet above the water, Faust said. And, while the rig is designed for use in water depths of 400 to 500 feet, the water at the Devil’s Paw drilling location will only be about 140 feet deep, he said.

One advantage of using a fixed jack-up platform for the drilling will be the ability to install a strong, heavy-duty steel riser pipe from the seafloor to the platform, rather than the more flexible type of pipe required for a floating drilling structure, Faust said. And that, in turn, enables the placement of the well’s blowout preventer on the platform, where it can be accessed easily, rather than in a mud-line well cellar on the seafloor.

As a further line of defense against a well blowout, should the surface blowout preventer fail, ConocoPhillips is placing a well capping device on the seafloor, to close off the well if necessary.

“That cap is in place before we start drilling the well and we drill through that,” Faust said.

Accommodating sea ice

The rig is not designed to operate in sea-ice conditions. But, although ConocoPhillips will use the rig at a time of year when sea at the drilling site should be clear of ice, there is the ever-present possibility of an unfavorable wind blowing ice floes into the area of the drilling operation.

To allow for the possibility of a threat from ice encroachment, ConocoPhillips has developed an ice alerts program, using satellite synthetic radar data showing sea-ice images that enable the plotting of sea-ice movements. This type of satellite technology can see through cloud, works in the darkness and images ice very effectively, Faust said.

Ice-alert circles

Essentially, the drilling team will plot three concentric ice-alert circles around the drilling location. Ice management vessels will investigate any ice that enters the outermost circle, about 50 kilometers from the drilling rig. If ice crosses the middle circle, no new drilling operations will start and the rig crew will begin preparations for a possible move from the drilling site. Once ice enters the inner circle, drilling operations will stop, the rig will jack down into the water and support vessels will tow the rig to safety, well away from the ice.

If the jack-up rig has to move off site, the well would be comprehensively sealed at the sea floor and the riser pipe removed, Faust told Petroleum News.

The diameters of the ice-alert circles may vary from day-to-day, and even within a day, depending on the observed speed of ice movement and the nature of the drilling operation being conducted — the longer the anticipated time taken to finish an operation, jack the rig down and tow it from the site, the larger the circles become.

If uninterrupted, the complete drilling of a single well, from rig-up to rig-down, should take about 40 days, 30 days of which would involve the actual drilling operations, Faust said. So, with the Chukchi Sea open water season lasting on average 100 to 120 days, there should be more than enough time to drill one well, with the possibility of a second well, he said.

Heavy-lift vessel

ConocoPhillips will use a heavy-lift vessel to transport the drilling rig from Singapore, hopefully all the way to the Chukchi Sea drilling site, Faust said. However, given the vagaries of the ice conditions, it may be necessary to stage the rig near the coast to the south, with tugs towing the rig into position once the ice has cleared, he said.

According to a Federal Register notice for an application for a marine mammal incidental harassment authorization that ConocoPhillips has submitted to the National Marine Fisheries Service vessels involved in the drilling operation will not arrive at the drill site until July 1 at the earliest, with drilling operations potentially taking place between July and October. A heavy-lift vessel will remove the jack-up rig from the drilling arena at the end of the drilling season, the notice says.

Staging location

The Federal Register notice also says that the location where ConocoPhillips may stage the drilling rig at the beginning of the drilling season, should ice conditions prevent the heavy-lift vessel delivering the rig all the way to the Chukchi Sea drilling site, is six miles offshore the Chukchi Sea coast, about 20 miles south of the village of Kivalina.

This choice of staging area location was based on proximity to infrastructure and the likelihood of ice-free conditions at the time when staging might be required, the notice says.

It became evident during the open water meeting that some Kivalina residents, presumably concerned about potential disturbance to subsistence hunting, are less than enthusiastic about the idea of having a jack-up rig parked near their village.

“We’re certainly listening to that and tying that into our plans as much as we can,” Faust said, commenting that, depending on ice conditions, one option might be to keep the rig on the heavy-lift vessel, rather than stage it.

Support fleet

ConocoPhillips anticipates needing nine vessels to support the drilling operation, with three vessels providing oil spill response support and the other vessels performing multiple roles, Faust said. Other than when used for shipping supplies, the support vessels will remain within five-an-a-half miles of the drilling rig, he said.

Wainwright will act as a supply base for the operation, with personnel being transferred to and from the offshore by helicopter, and with a landing craft carrying perishable supplies to a supply vessel. After hearing worries about possible noise and disturbance in Wainwright, ConocoPhillips has built a road to an out-of-town helipad and is in discussion with people from the community about appropriate helicopter routes, Faust said. And, to minimize the number of crew changes required, the company is using a drilling rig with large crew quarters, he said.

Faust said that in working with local North Slope communities ConocoPhillips has been addressing concerns and taking advice based on traditional knowledge.

“Over the past four years the plan has changed pretty significantly, in many ways because of the feedback we’ve gotten in the communities and the kinds of observation that the hunters and whalers have told us about,” Faust said.



Did you find this article interesting?
Tweet it
TwitThis
Digg it
Digg
Print this story | Email it to an associate.

Click here to subscribe to Petroleum News for as low as $69 per year.


Petroleum News - Phone: 1-907 522-9469 - Fax: 1-907 522-9583
[email protected] --- http://www.petroleumnews.com ---
S U B S C R I B E

Copyright Petroleum Newspapers of Alaska, LLC (Petroleum News)(PNA)©2013 All rights reserved. The content of this article and web site may not be copied, replaced, distributed, published, displayed or transferred in any form or by any means except with the prior written permission of Petroleum Newspapers of Alaska, LLC (Petroleum News)(PNA). Copyright infringement is a violation of federal law subject to criminal and civil penalties.




Drilling some virtual Chukchi Sea wells

As part of its planning for exploration drilling in the Chukchi Sea in 2014, ConocoPhillips has been simulating its drilling project, drilling “virtual wells” during summer open water seasons, Mike Faust, the company’s Chukchi Sea exploration project manager, told the National Marine Fisheries Service’s annual Arctic Open Water Meeting on March 7. Each summer for the past three years the exploration team has gone through an exercise of drilling wells on paper, using actual weather and ice conditions to envisage how a real drilling operation might have progressed, Faust said.

“We’ve sat in a room every morning and pretended … we were really drilling the well,” Faust said. “So we looked at every operation, every step. We took the ice conditions into effect … we took the weather conditions into effect that day and made operational decisions as if we were really drilling the well.”

Lessons learned

The outcome has been a lengthy list of lessons learned that feed into revisions to ConocoPhillips’ drilling plans — in the last year alone, the virtual drilling exercise generated about 200 lesson-learned items, Faust said.

One lesson learned from the first virtual drilling season related to the synthetic radar satellite imagery that the company plans to use to track the movement of sea ice, to enable the company to move the drilling rig out of the way of any ice floes that might encroach the drilling area. Subsistence hunters had correctly pointed out that ice can move and change very rapidly, Faust said. And, having realized that it would be necessary to obtain satellite data much more frequently than every three days, the frequency that the company had originally assumed, ConocoPhillips now buys satellite imagery twice a day — during actual drilling operations it may become necessary purchase imagery even more frequently than that, Faust said.

Operations center

Another lesson learned from virtual drilling has been the need for a state-of-the-art operations center, where sea-ice imagery, vessel locations, aircraft locations, personnel deployment data and other information about the drilling project can be displayed real-time in graphic form, Faust said.

“So we’ve built a really nice operations center across the street from the ConocoPhillips building (in Anchorage), and that will be manned 24/7 when we’re out there actually operating,” he said.

For this year’s virtual drilling exercise ConocoPhillips is involving all of its contractors, to enable the contractors to practice with the company, simulating the anticipated plan for 2014, Faust said. Caryn Rae, manager of the ConocoPhillips environmental studies program for the Chukchi Sea, said that this summer’s virtual drilling program will also reach out to the North Slope communities, enabling the practicing of daily reporting, for example.

Rae said the company is still figuring out the specifics of community involvement in the drilling simulation but that the company has been gathering information from the communities about their subsistence hunting activities.

“We will have that information at our disposal as we go through our virtual drill,” she said.

—Alan Bailey