CINGSA short of base gas for facility Construction work near complete in July; base gas fill delayed because contracted gas not delivered, more sought from producers Kristen Nelson Petroleum News
Cook Inlet Natural Gas Storage Alaska, CINGSA, told the Regulatory Commission of Alaska Aug. 13 that it has not received the base gas it needs to ensure gas can be withdrawn by customers at optimum rates this coming winter.
The natural gas storage facility, designed to hold up to 11 billion cubic feet of working gas, officially began operations May 31.
CINGSA said that while the commission has closed the docket and progress reports are not required, it will continue to file monthly reports until the facility is fully operational.
The issue with base gas began in March 2011 when CINGSA contracted with an unnamed Cook Inlet producer to provide 3.24 bcf of base gas.
“Sufficient base gas is needed to ensure that pressures in the storage reservoir are high enough to permit customers to withdraw gas from the CINGSA Storage Project within design parameters,” CINGSA told the commission.
However, the producer with which it contracted “now asserts that, under this agreement, it had the option to sell the base gas to CINGSA but not the obligation to do so,” a contention with which CINGSA said it disagrees.
“CINGSA believes that gas intended to be sold to CINGSA has instead been exported to Japan as LNG at a substantially higher price than CINGSA had agreed to pay,” it told the commission.
Withdrawal service available CINGSA said it would be able to provide withdrawal service to customers even with lower levels of base gas, but believes 7 bcf of base gas “would allow the project to operate as designed.”
CINGSA said it has secured 5 bcf of base gas, including 0.5 bcf of base gas under a July 11 contract with ConocoPhillips Alaska. Deliveries of that gas are expected beginning in August.
CINGSA said it is attempting to secure additional base gas “from various Cook Inlet area producers, so that gas can be withdrawn by customers from the CINGSA Storage Project at optimal rates during the 2012-13 winter heating season.”
July work Injection began April 1 and July injection rates ranged from about 25 million to 52 million cubic feet per day, “depending on customer nominations and the availability of base gas,” CINGSA told the commission.
Subsurface engineering work during July included re-perforation of wells 2, 3, 4 and 5 to improve injection and withdrawal capability. All wells showed improved deliverability following the work, CINGSA told the commission; the same work is planned for well 1 as soon as a coiled tubing unit is available.
CINGSA said it has received one or two noise complaints from nearby residents and “is in the process of identifying and implementing sound attenuating devices to reduce noise levels further.”
The compressor plant was idle during a scheduled shutdown of the Kenai Nikiski Pipeline and another round of sound level data was collected then, with some of the sampling focused on the area where residents had complained.
All station piping was completed in July, and with construction work completed in the month, CINGSA said surface facilities are approximately 93 percent complete.
The CINGSA owners are Semco Energy, MidAmerican Energy Holdings Co., Cook Inlet Region Inc. and First Alaska Capital Partners.
|