Press report misleading

Kay Cashman

A British newspaper received a call from BP “to make it clear” that a North Slope gas pipeline project “is not on the shelf,” BP Exploration (Alaska) Inc. spokesman Ronnie Chappell told PNA Feb. 15.

The call followed an article in the newspaper about a presentation BP’s top executives made to analysts Feb. 14. The article’s headline said BP was ready to “shelve” the North Slope gas pipeline project.

“It seemed to me that the headline really didn’t reflect what John Browne said. Nowhere did he say BP was shutting down the project,” ExxonMobil spokesman Bob Davis told PNA. “He said the project was uneconomic but that’s been said before. … Nothing has changed. We’re looking at the results of the gas study. … We expect to make an announcement at end of March. …

“In my view, the headline was more sensational than the body of the article,” Davis said, pointing out the fact that headlines are generally written by someone other than the author.

John Browne, BP Plc’s CEO, did tell analysts that the $15 billion to $17 billion project was not yet competitive; something the big three North Slope gas owners have been saying for more than a year.

Dick Olver, head of upstream operations for BP Plc, told analysts that BP did not see a gas pipeline transporting North Slope gas to Lower 48 markets until 2008, but “perfectly likely in 2009 and it could be 2010.”

Proponents of the pipeline have targeted 2007 as the mostly likely start-up date for gas to flow, but Chappell said “The stars would have had to line up and everything be perfect to achieve 2007.

“They were talking 2007 a year ago. This is a year later and we still don’t have an economic project. …

“I guess I don’t understand what the hub hub is about. We have been telling people that the project is not competitive. We have also been telling them we don’t think the project is competitive — yet. … “We’re pushing to develop a competitive project. We’re not there yet,” Chappell said.

“We have two criteria for this project to move forward: It has to be economic and everybody has to support it,” he said, saying the next step was getting enabling legislation passed in Washington, D.C.






Petroleum News - Phone: 1-907 522-9469 - Fax: 1-907 522-9583
[email protected] --- http://www.petroleumnews.com ---
S U B S C R I B E

Copyright Petroleum Newspapers of Alaska, LLC (Petroleum News)(PNA)©2013 All rights reserved. The content of this article and web site may not be copied, replaced, distributed, published, displayed or transferred in any form or by any means except with the prior written permission of Petroleum Newspapers of Alaska, LLC (Petroleum News)(PNA). Copyright infringement is a violation of federal law subject to criminal and civil penalties.