HOME PAGE SUBSCRIPTIONS, Print Editions, Newsletter PRODUCTS READ THE PETROLEUM NEWS ARCHIVE! ADVERTISING INFORMATION EVENTS PETROLEUM NEWS BAKKEN MINING NEWS

Providing coverage of Alaska and northern Canada's oil and gas industry
May 2002

Vol. 7, No. 20 Week of May 19, 2002

Drilling will be challenge at Point Thomson, says Williams

Kristen Nelson, PNA editor-in-chief

The industry has drilled into 10,000 psi reservoir pressures. And drilled extended reach wells of more than three miles. The trick at Point Thomson will be doing both at the same time, Jack Williams, Alaska production manager for ExxonMobil Production Co. told the Resource Development Council May 16.

ExxonMobil is the operator and 36 percent working interest owner at the Point Thomson unit on the eastern side of the North Slope, where a gas cycling project is planned to develop the high-pressure condensate field.

The company began filing development permits last summer and Williams said ExxonMobil has been waiting to start talking about the project until the notice of intent was published in the Federal Register April 19, initiating the environmental impact statement process.

Development decision in 2003-2004

The project is in the early stages, said Williams, but if it stays on schedule a final development decision would be made by the working interest owners in late 2003 or 2004.

The basis of that decision, he said, will be project costs and the project’s ability to get permits.

If the project is approved by the Point Thomson owners, start-up is anticipated for year-end 2006. The owners would need permitting certainty by the end of 2003, Williams said, so that long-lead equipment could be ordered in time for a 2006 sealift.

Development drilling would begin in the winter of 2005-2006, with extended reach wells going out under the Beaufort. Williams said technology since the field was discovered means a much smaller footprint. When development was discussed in the late 1980s, he said, the companies expected to need eight drilling pads to accommodate wells producing at less than 40 million cubic feet a day. This plan has two drill pads and one re-injection pad and the wells will produce at more than 100 million cubic feet per day.

Williams said rig modifications will be required for Point Thomson and that a two-rig program is most likely.

Peak production of 75,000 bpd

Reserve estimates are 8 trillion cubic feet of gas and 400 million barrels of condensate at the 116,724-acre Point Thomson unit. Peak production is estimated at 75,000 barrels of condensate per day.

The condensate will be extracted from the gas and shipped to market and the dry gas will be injected back into the reservoir for pressure maintenance and future use.

The high-pressure re-injection rate will be higher than any currently being done, he said, and heavy drilling mud will be required for the wells.

Williams said the working interest owners have spent some $800 million over the years on leases and work at Point Thomson. Development cost, in addition to that already spent, is expected to exceed $1 billion and include a 22-mile pipeline to Badami.

The economics of the project are based on a 30-year condensate production and gas cycling project, Williams said, but that wouldn’t prohibit gas sales at some point.

Principal owners are operator ExxonMobil, BP, ChevronTexaco and Phillips.





Want to know more?

If you’d like to read more about Point Thomson, go to Petroleum News • Alaska’s Web site and search for these recently published articles. The articles listed do not include royalty gas or gas pipeline issues related to Point Thomson, but they can also be found in PNA’s archives.

Web site:

www.PetroleumNewsAlaska.com

2002

• April 21 Murphy continues to appeal state’s Point Thomson decision

2001

• Dec. 9 ExxonMobil working to make Point Thomson economic

• Nov. 18 Exxon’s Point Thomson will be North Slope’s first high-pressure condensate field

• Oct. 14 Murphy appeals Point Thomson decision, charges forced integration

• Oct. 7 Point Thomson pegged at $1.3 billion; offshore compressors not needed for over-the-top route

• Sept. 30 State accepts 18th plan of development for Point Thomson

• August Working interest owners submit Point Thomson development plan

• August Point Thomson unit aligned, Phillips now an owner

• August State conditionally approves Point Thomson unit expansion-contraction

• June Point Thomson owners want production flexibility

• May State asks for production from Point Thomson unit next to ANWR by 2008

• April Atofina demands its leases be included in Point Thomson unit

• April Exxon’s plan for Point Thomson brings field closer to development

• January Point Thomson unit owners negotiating unit expansion with state


Petroleum News - Phone: 1-907 522-9469 - Fax: 1-907 522-9583
[email protected] --- http://www.petroleumnews.com ---
S U B S C R I B E

Copyright Petroleum Newspapers of Alaska, LLC (Petroleum News)(PNA)©2013 All rights reserved. The content of this article and web site may not be copied, replaced, distributed, published, displayed or transferred in any form or by any means except with the prior written permission of Petroleum Newspapers of Alaska, LLC (Petroleum News)(PNA). Copyright infringement is a violation of federal law subject to criminal and civil penalties.